With the above data, and Table 22, page 120, the amount of cement and sand required for a specified number of brick, or for a given number of yards of masonry, can readily be determined.
Ordinarily 0.75 barrel of unslaked lime or 1 barrel of lime paste and 0.75 cu. yd. of sand will lay a thousand bricks.
wages for ten hours of mason and helper.
Table 56 and Table 57 give the actual labor, per cubic yard, required on some large and important jobs.
Table 57 shows the cost of the labor for five brick buildings forming part of a large manufacturing plant.$ Buildings No. 1 and 2 were long and low, with about equal amounts of S-inch . and 13-inch walls; buildings No. 3 and 4 had larger proportion of 13-inch wall; buiding No. 5 contained more brick than any of the others, and had 13-inch walls, with some 17-inch and 22-inch walls.
On building No. 1 local bricklayers were used at 50 cents per hour, but for the other buildings city bricklayers at 60 cents per hour were imported. The latter did better work and more of it, as shown by the table. About two or three weeks after the 60-cent brick layers started work, the inspector, being dissatisfied with the way the work was going, began preparing careful estimates of the brick laid each week and of the cost per 1,000 for bricklayers and helpers. Within three weeks after the first estimate, the output per brick layer had increased over 40 per cent, and about 30 per cent increase was maintained.
The total average cost of the brick masonry is as follows: _ _ _ Total Cost of Brick Masonry. The following is the cost of 660.cu. yd. (net) of brick masonry (307,000 brick) in a wall 18 inches thick and 25 feet high. The joints were to of an inch thick; and 465 brick laid a cubic yard.*