112. Ramming Concrete. Immediately after concrete is placed, it should be rammed or puddled, care being taken to force out the air-bubbles. The amount of ramming necessary depends upon how much water is used in mixing the concrete. If a very wet mixture is used, there is danger of too much ramming, which results in wedging the stones together and forcing the cement and sand to the surface. The chief object in ramming a very wet mixture is simply to expel the bubbles of air.

The style of rammer ordinarily used depends on whether a dry, medium, or very wet mixture is used. A rammer for dry concrete is shown in Fig. 8; and one for wet concrete, in Fig. 9. In very thin walls, where a wet mixture is used, often the tamping or puddling is done with a part of a reinforcing bar. A common spade is often em ployed for the face of work, being used to push back stones that may have separated from the mass, and also to work the finer portions of the mass to the face, the method being to work the spade up and down the face until it is thoroughly filled. Care must be taken not to pry with the spade, as this will spring the forms unless they are very strong.

113. Bonding Old and New Concrete. To secure a water-tight joint between old and newconcrete, requires a great deal of care. Where the strain is chiefly compressive, as in foundations, the surface of the concrete laid on the previous day should be washed with clean water, no other precautions being necessary. In walls and floors, or where a tensile stress is apt to be applied, the joint should be thoroughly washed and soaked, and then painted with neat cement or a mixture of one part cement and one part sand, made into a very thin mortar.

In the construction of tanks or any other work that is to be water-tight, in which the concrete is not placed in one continuous operation, one or more square or V-shaped joints are necessary. These joints are formed by a piece of timber, say 4 inches by 6 inches, being imbedded in the surface of the last concrete laid each day. On the following morning, when the timber is removed, the joint is washed and coated with neat cement or 1:1 mortar. The joints may be either horizontal or vertical. The bond between old and new con crete may be aided by roughening the surface after ramming or be fore placing the new concrete.

114. Effects of Freezing of Concrete. Many experiments have been made to determine the effect of freezing of concrete before it has a chance to set. From these and from practical experience, it is now generally accepted that the ultimate effect of freezing of Port land cement concrete is to produce only a surface injury. The setting and hardening of Portland cement concrete is retarded, and the strength at short periods is lowered, by freezing; but the ultimate strength appears to be only slightly, if at all, affected. A thin scale about inch in depth is apt to scale off from granolithic or concrete pavements which have been frozen, leaving a rough instead of a troweled wearing surface; and the effect upon concrete walls is often similar; but there appears to be no other injury. Concrete should not be laid in freezing weather, if it can be avoided, as this involves additional expense and requires greater precautions to be taken; but with proper care, Portland cement concrete can be laid at almost any temperature.

There are three methods which may be used to prevent injury to concrete when laid in freezing weather: First: Heat the sand and stone, or use hot water in mixing the con crete.

Second: Add salt, calcium chloride, or other chemicals to lower the freezing point of the water.

Third: Protect the green concrete by enclosing it and keeping the temperature of the enclosure above the freezing point.

The first method is perhaps more generally used than either of the others. In heating the aggregate, the frost is driven from it; hot water alone is insufficient to get the frost out of the frozen lumps of sand. If the heated aggregate is mixed with water which is hot but not boiling, experience has shown that a comparatively high temperature can be maintained for several hours, which will usually carry it through the initial set safely. The heating of the materials also hastens the setting of the cement. If the fresh concrete is covered with canvas or other material, it will assist in maintaining a higher temperature. The canvas, however, must not be laid directly on the concrete, but an air space of several inches must be left between the concrete and the canvas.