Detailing from Framing Plan

beam, fig and detail

Page: 1 2 3 4 5 6 7 8 9

2. Make details covering the 10 to 13-inch beams in Fig. 20S.

3. Make a schedule of tie rods and of field bolts required for all framing shown in Fig. 20S.

4. Suppose that in Fig. 199 the cast iron columns had a 12-in., 31-lb. beam instead of the 15-in. beam, a 7-in. instead of the 10-in. beam, and a 9-in. instead of the 12-in. beam, and that all beams were flush on top and the other features the same as shown in Fig. 210. Make a detail of such a column.

5. IN fake a bill of material for the column shown in Fig. 224.

6. Given a portion of a framing plan as shown in Fig. 226. Make shop details of (a) beam No. 1 resting on the column. (b) beam No. 2, and (c) channels No. 3 and 4.

7. Given a. beam box girder framed between two columns as shown in Fig. 227. Make a shop detail of this girder using a uniform pitch of rivets of 3 in. in the plates.

S. Given a lintel composed of two 10-in., 15-lb. channels framed between two columns, the channels being placed with the flanges turned in, 10 in. back to back, and 14 ft. S in. between the faces of columns. 'Make a complete shop detail and older for all parts.

9. Given a pit under an elevator to be framed with 3 X 3-in., 6.6-lb. Ts, 17-in. on centers, to receive terra cotta tile. These Ts frame between the webs of 15-in., 42-lb. 1-beams at each end, which are 7 ft. 3 in. center to center. The distance from the top of the beams to the bottom of the flange of the Ts is 6 in. Make a shop detail of the Ts.

10. Given a portion of a framing plan as shown in Fig. 22S. Make a shop detail of beams No. 1 and 2 which are framed between columns.

11. In the above plar make detail covering beams, No. 4 and 5.

12. Given a 15-in,, 42-1b. beam framed between the webs of two columns, 20 ft. S in. center to center on a line perpendicular to the axis of the webs, and the center of one column is 1 ft. 9 in. off from the other in the direction of the webs. The webs of the columns are in. thick. The beam has a 12-ft., beam framed to it, 2 ft. 1 in. from the center of one column, the tops being flush. There are also holes for two lines of 1-in, tie rods. Make shop detail.