Methods of Wiring

wires, run and tubes

METHODS OF WIRING.

In

running wires, the shortest and most direct route should, of course, be taken between the battery, bells, and bell pushes. There are two cases to be considered. The better method is that in which the wires are run before the building is completed, and the wiring should be done as soon as the roof is on and the walls are up. In this case the wires are usually run in zinc tubes secured to the walls with nails. The tubes should be from # inch to , inch in diameter, preferably the latter. It is better to place the wires and tubes simultane ously, but the tubes may be put in place first and the wires drawn in afterward, although this latter plan has the objection that the insulation is liable to become abraded when the wires are drawn in In joining up two lengths of tube, the end of one piece should be opened up with the pliers so that it may receive the end of the other tube, which should also be opened up, but to a less extent, to prevent wear upon the insulation. Specially prepared paper tubes are sometimes substi tuted for the zinc.

If the building is completed before the wiring is done, the concealed method described above cannot be used, and it is neces sary to run the wires along the walls supported by staples, where they will be least conspicuous. Fig. 2 shows ordinary double pointed tacks, Fig. 3 shows an insulating saddle staple which is to be recommended. Two wires should never be secured under the same staple if it can possibly be avoided, owing to the danger of short circuits. With a little care it is usually possible to con ceal the wiring behind the picture moulding, along the skirting-board, and beside the door but where it is impossible to conceal it, a light ornamental casing to match the finish of the room, may be used. It is sometimes advisable to ase twin wires or two insulated wires run in the same outer covering.

In some cases it is well to run the wires under the floors, laying them in notches in the tops of the joists or in holes bored about two inches below the tops of the joists.